1. Ensure all specified materials and dimensions are in accordance with the drawing.
2. Fill all holes and deficiencies between walls and floors.
3. Install resilient flanking strips around the perimeter of the floorboard to isolate the floor from walls and skirting.
4. Ensure resilient strip is continuous and pre-bonded to the timber batten. Any services should not bridge the resilient strip.
5. Install slab insulation tightly fitted between the joists, with no gaps and ensure the air cavity is not bridged at any point.
6. Screw the GenieClip LB3 straight to the base of the joists. Do not over tighten.
7. Snap furring channel into the GenieClip LB3 and make joins between clips with a 150mm overlap.
8. Fix boards to steel channel with long edges at right angles to the framing.
9. Affix the second acoustic plasterboard with staggered joints. Ensure a 3mm gap is maintained around the perimeter and seal with acoustic sealant.
10. Ensure ALL flanking routes are supressed.